Speeding up the implementation of traffic works
Updated : Friday, May 25, 2018 4:50 PM (GMT+0700)

Takingadvantage of fine weather, investors and construction units of traffic works inthe province have mobilized maximum means and human resources to accelerate constructionprogress. Numerous works strive to be completed this year on schedule.

 
Workers on duty at Da Rang Bridge

These days, the atmosphereof construction site of Da Rang Bridge, Tuy Hoa city is very exciting andurgent. Motorbikes and equipment here are busy at both day and night. With 5construction points, hundreds of workers are focusing on working hard.

According to Thang LongProject Management Board (Ministry of Transportation) - the unit implementingand managing the project, so far, the project progress basically meets theschedule. The contractor has completed such items as sheds, equipment, roadsand beam ground. As for the XL01 package, the contractor has finished 10 out of30 bored piles and 4 out of 56 beams. Also, the XL02 package has completed 2out of 30 bored piles and is finishing beam casting ground and concretebatching plant.

Not only Da Rang Bridge, thecontractor of the route connecting two provinces of Phu Yen and Gia Lai is alsoorganizing many construction points to speed up progress. This route isinvested in the BT form (built - transferred) with scale of level IVmountainous road and total length of 61,3 km. The project is being implemented inphase 1 with 31km road through Phu Yen province and total investment of morethan 1.500 billion dongs.

According to Mr. Nguyen VietBien, Head of the directing board of the project of upgrading the route connectingtwo provinces of Phu Yen and Gia Lai, after the Lunar New Year, in sunnyweather, the contractor has mobilized maximum human resources and equipment. Onthe route, the contractor has organized 18 construction points for the project’simplementation.

After a long time of beingslow, the construction progress of Dinh Ong Bridge has gradually improved. Mr.Nguyen Van Vien, Deputy Director of the provincial management board ofconstruction investment projects, lets known: at the construction site, thecontractor is mobilizing about 100 workers with dozens of equipment toimplement the project. Up to now, some items have reached and exceeded theschedule; particularly completing T8 post, T9 post, temporary bridges... Tocomplete the work as signed contract and the PPC’s direction of completion in2018, the investor has requested the contractor (Dong A International GroupJSC) to urgently add technical staff to the management board, workers toconstruction site and organize 3 working shifts per day. In addition, thecontractor has arranged more equipment, motorbikes; the investor has consideredto adding subcontractors for the project.

Meanwhile, according toThang Long Project Management Board, the contractor of Da Rang Bridge does notonly organize many construction points but also organizes 3 working shifts perday. It is expected that by August, the entire downstream section will becompleted to avoid damages caused by floods.

The investor is currently urgingthe contractor to increase human resources and equipment to soon complete worksahead of schedule. According to Mr. Nguyen Viet Bien, the contractor isfocusing on constructing sections that handed over ground and completingremaining items of the project of upgrading the route connecting two provincesof Phu Yen - Gia Lai in 2018.

Source:Phu Yen Newspaper

Translatedby KHUONG THAO

Write your comment here
Name:
Email:
Title:
Comment:
© PhuYen Newspaper- Editorial Board: 62 Le Duan, Tuy Hoa City, Phu Yen Province
Tel: (84-057).2211110 - (84-057).3842488, Fax: (84-057).3841275
Email: tsbpy@dng.vnn.vn
Designed by nTek